Maple/Middlebelt Construction Part 2 – Middlebelt Remains Open During Construction

 

MAPLE ROAD AT MIDDLEBELT ROAD IN WEST BLOOMFIELD TWP. EXPECTED TO CLOSE MARCH 30 FOR CONTINUED WORK

The Road Commission of Oakland County (RCOC) expects to close Maple Road at Middlebelt Road in West Bloomfield Township on Monday, March 30, for continued construction work on the roundabout.

Construction is expected to be completed and Maple Road re-opened in early June; however, the anticipated opening date is fluid and could change based on weather and potential impacts of the coronavirus (COVID-19) pandemic.

Northbound and southbound Middlebelt Road at Maple Road will remain open to traffic; however, access to eastbound and westbound Maple Road will be closed.

The Maple/Middlebelt roundabout was mostly constructed last year. However, some work remains to be completed this year, including:

• Concrete work on the center island
• Americans with Disabilities Act-compliant sidewalks and crosswalks
• Installation of High-intensity Activated crossWalK (HAWK) beacons at the pedestrian crossings
• Street lighting and behind-the-curb restoration of landscaping

For more information on the Maple/Middlebelt Road roundabout and culvert replacement project, visit: https://www.rcocweb.org/479/MapleMiddlebelt-Road-Roundabout.

With Middlebelt remaining open we think this will have very little impact on our subdivision.   As always if you do notice cut through traffic speeding through the subdivision please call the the police city dispatch at 248-871-2610

 